Implementation methodology

MyTower GTM modules are modular and can be implemented individually or combined in a roadmap; they usually integrate with ERP, TMS, WMS, customs systems, brokers, and trade content sources.

PhaseObjectiveTypical activities
1. Scope & Fit-GapConfirm business scope and target countries/entities/processesProcess workshops, legal scope, system landscape, data sources, current pain points, target users
2. Business BlueprintDefine target operating model and functional designFuture process, data model, roles, workflows, business rules, exception handling, reporting needs
3. Integration BlueprintDefine inbound/outbound data flowsERP/TMS/WMS interfaces, APIs/SFTP, mapping, frequency, ownership, error handling
4. Configuration & BuildConfigure the module and build required mappings/rulesRoles, views, statuses, business rules, reference data, workflows, interfaces
5. Data Migration / Initial LoadLoad starting data into MyTowerProducts, partners, declarations, historical data, BOMs, supplier data, stock, licenses, documents
6. SIT / Integration TestingValidate technical and functional end-to-end flowsInterface tests, rule execution, status updates, error scenarios, regression checks
7. Training & ChangePrepare operational teamsKey-user training, SOPs, work instructions, role-based training, broker/supplier onboarding
8. UATLet business users validate real-life scenariosBusiness test scripts, edge cases, user feedback, corrections, sign-off
9. Cutover & Go-LiveMove from project to productionData freeze/load, activation of interfaces, user access, first transactions, monitoring
10. Hypercare & RunStabilize and transition to supportDaily checks, issue triage, KPI monitoring, backlog, handover to support/managed services

Module-specific activities and customer dependencies are described in Module implementation guides.